List of Wireless 802.11n Buildings in Progress

Legend:

Service Cutover - date scheduled for new 802.11n service implementation
Onsite - RF Design complete, onsite Cable installation and AP placement underway
Planning - RF Design activities underway

As of January 24, 2012


(new) IVEY Building - Service Cutover - in progress (phased in with construction project)
Physics & Astronomy - Service Cutover - in progress (phased in with renovation project)
Spencer Hall (IVEY) -  Service Cutover - Deferred
 Biotron - Service Cutover - January 26, 2012
Dental Sciences Building - Onsite
Western Sciences Center - Onsite
Middlesex College - Planning
Collip Building - Planning
Faculty of Education - Planning
Visual Arts - Planning
Staging Building - Planning
Talbot College - Planning
Music Building - Planning